Project Information
CST-2026-047 · v2ClientSyarikat Kenanga Sdn Bhd
Project NameOffice Renovation – Phase 2
Period2026 / Q1
Prepared ByAhmad Razif
Date Prepared20 Feb 2026
Submitted On21 Feb 2026, 09:14 AM
ScopeFull renovation of Level 3 office space including partitioning, ceiling works, flooring, and electrical upgrade.
Line Items Summary
6 items · v2 (latest)1.Supply & install drywall partitioning (10mm) — 250 m² × RM 85.00
21,250.00
2.False ceiling with cornice (gypsum board) — 320 m² × RM 65.00
20,800.00
3.Floor vinyl tiles installation — 300 m² × RM 55.00 ▲ CHANGED
16,500.00
4.Electrical rewiring & light points — 60 pts × RM 180.00
10,800.00
5.Painting – walls & ceiling (2 coats) — 620 m² × RM 12.00
7,440.00
6.Site supervision & project management — 1 lot × RM 5,000.00
5,000.00
SubtotalRM 81,790.00
Discount (5%)– RM 4,089.50
SST (8%)+ RM 6,216.04
GRAND TOTALRM 83,916.54
Version History
v2 (Current)
21 Feb 2026 · Ahmad Razif — revised floor tiles unit price
v1
20 Feb 2026 · Ahmad Razif — initial submission
Approval Decision
⚠️ Reviewing v2 · Changes highlighted in yellow
Activity Timeline
✓
Costing Created
S
Submitted for Approval (v1)
R
Revision Requested
"Please revise floor tile unit price — RM 50 is too low for this spec."
E
Revised & Resubmitted (v2)
Awaiting Approval